Project team
Structural Engineer:Civic Engineers
Main Contractor:Kier Construction
Phase three of Park Hill regeneration offers a masterclass in reusing structures
Few buildings provide as valuable a template for the retrofit of existing concrete structures as the 1960s Park Hill estate in Sheffield. This is Europe’s largest listed building, and is being regenerated in a multi-phase programme by developer Urban Splash. In phase three, local practice Whittam Cox has taken one of the lower blocks of single and double-storey flats and converted it into a terrace of three-storey townhouses for student living.
This attempts to address one of the main failings of the estate: single-tenure housing rather than a mix of residents and uses. But the project is also notable for its strict strategy of retaining as many of the physical elements of the once-derelict structure as possible.
This process began with the original drawings, produced by Arup in the 1950s, which were used to develop a 3D BIM model of the existing building. From this, the team could calculate the tonnage of the frame and make a conservative estimate of its embodied carbon. This weighed in at 1,050,480 tonnes CO2e, which will now continue to be useful for decades to come. In addition, the explicit strategy of retaining non-structural elements, such as floor screeds, concrete balconies, blockwork partitions and stairs, saved a further 577 tonnes CO2e.
Material efficiency was also improved by the decision to leave much of the internal structure exposed. The original plaster had protected the boardmarked concrete beneath, and could be wet-scraped away and simply finished with an anti-carbonation coat. Elsewhere, more painstaking concrete restoration was needed. Many of the balustrade spindles, for example, showed severe spalling, but rather than removing them, the team managed to save 90% through careful repair work.
Throughout the project, a conservation-led approach has been taken, with the architects keen to express rather than conceal the repairs,” says Matt Borland, associate director at Whittam Cox. “We went through a lengthy process with the conservation officer to agree a colour for the patch repairs. The concrete is quite unique, with a brown tone from the aggregate mix that was used, and it varies a bit as well because of the way they cast it originally.
There were also a number of different textures – some where you could still see the wood grain from the board marking, and other that were really badly washed out.” The decision was taken to use a smooth repair mortar with a consistent colour throughout, so that repairs would be visible and read as part of the history of the building. All of the repaired concrete was finished with a clear, matt protective coating.
Cold bridges also proved a challenge – the estate having been designed before avoidance of thermal bridging was a consideration. Passivhaus modelling was used to work out how thermal improvements could be made. Insulated linings have been used as much as possible to create a break between the external and internal structure, helping to achieve a weighted U-value of 0.22W/m2K.
The as-built operational emissions of the townhouses have been measured at 33kgCO2e/m2, but Whittam Cox expects this to improve and is continuing to monitor energy use on a meter-by-meter basis. The building is also all-electric – by replacing gas for heating and hot water, it will rely less and less on fossil fuels as the national grid switches over to renewable sources.